2 Chapter 2. Project Planning Page 1 of 1
2
Print page | Print Chapter | Print Brochure
 
The project client should involve the Aircrete manufacturer in feasibility discussions to enable the Aircrete producer to use their product knowledge to add value at the conceptual stage. The client’s aims, objectives, needs and expectations
should be made clear.

Different levels of risk pertain at each phase of the construction process i.e. the earlier a risk is eliminated the better. Risks should not be transferred down the supply chain e.g. design and other risks should not be transferred to the construction phase but be resolved before work commences on site.

The process should be examined systematically to estimate the risks associated with each phase. Allowances should then be made for these.

The project planners should provide the Aircrete manufacturer with the following information at an early stage in the planning process:

Location and type of project
Size of project
Project programme
Project partners
Site information e.g. storage facilities

The Aircrete manufacturer should be consulted for advice on the Best Practice Aircrete solutions to enable correct specifications to be drawn up.

When the project objectives are made clear, the Aircrete manufacturer should advise on all aspects of the supply chain, conceptual design and relevant methods of construction. The early involvement of the manufacturer with their advice on Best Practice solutions leads to lowering costs by working efficiently rather than by merely going for lowest cost first.

Ideally, a visit to an Aircrete plant should be arranged with the manufacturer to acquire a better understanding of the material and its manufacture.

From the beginning and throughout the project, feedback and communication between all participants should be continuous to obtain maximum client satisfaction.

All project participants are encouraged to support the vision of an efficient construction process which exceeds the client’s expectations. This can only be fully achieved when conflict between the various parties is eliminated and team work ensues. The integrated team produces better contractual relationships and oils the mechanism for a smoother delivery of the completed project.

Aircrete manufacturers are available to give advice on the suitability and availability of alternative Aircrete solutions when required by telephone, email, letter, and fax or in the enquirer’s office. Details of the Autoclaved Aerated Concrete Products Association web site and contact details for all UK Aircrete manufacturers are given at the end of this code.








Aircrete Project Planning Properties Design Specification Procurement Construction References Introduction Index